Early on the morning of 12 November 2023, a section of the Silkyara–Barkot road tunnel in Uttarakhand’s Uttarkashi district caved in. Forty-one construction workers were on the far side of the fall. The collapse had struck between 205 and 260 metres from the Silkyara entrance, and the men were beyond the 260-metre mark, so the debris sealed their only way out (Business Standard, 2023).
What followed was one of the longest rescue operations India has seen. It lasted 17 days and more than 400 hours, and it ended on 28 November with all 41 men alive (Business Standard, 2023). At least 13 agencies took part (ThePrint, 2024a). People across the country celebrated the end. This article looks at the parts that are remembered less often: who the men were, why heavy machines failed where men with hand tools succeeded, what happened to the workers afterwards, and what a government committee later concluded about why the tunnel collapsed. On 28 November, it will be three years since the rescue.
The Silkyara tunnel is part of the Centre’s Char Dham project, which aims to give all-weather road connectivity to four Hindu pilgrimage sites. About 4.5 kilometres long, it links Silkyara and Dandalgaon and was expected to cut an hour from the journey between the two places once finished. The builder was Navayuga Engineering Company, working for the National Highways and Infrastructure Development Corporation Limited, or NHIDCL (Business Standard, 2023; The Week, 2024).
The trapped men were migrant workers. According to ThePrint, of the 41, fifteen came from Jharkhand, eight from Uttar Pradesh, five each from Bihar and Odisha, three from West Bengal, two each from Uttarakhand and Assam, and one from Himachal Pradesh (ThePrint, 2024a). Al Jazeera described them as low-wage construction workers, mostly from other northern and eastern states (Al Jazeera, 2023).
Contact with them came quickly. The next day, authorities reached the workers through the pipe that had been used to supply oxygen. But more rubble fell that day, stretching the debris over about 30 metres (Business Standard, 2023). From then on, the story became a race between the speed of the rescuers and the instability of the mountain.
The first plan was to drill a horizontal escape passage with a heavy auger machine. The first auger, owned by the state hydropower corporation, failed, and on 15 November the Indian Air Force flew in a second one from the United States. The new machine was installed the next day, and on 17 November it drilled through 24 metres of debris. Then the work stopped, because a loud sound and movement in the earth raised fears of another collapse (Business Standard, 2023).
By 18 November, horizontal boring was judged too risky. The next day, officials launched four alternatives at once: a drift tunnel, micro-tunnelling, blasting from the Barkot side, and vertical drilling from above. On 20 November, they pushed a six-inch pipeline through the debris to send in food and called in international tunnelling experts. Drilling resumed on 21 November, and by 22 November the auger had reached 48 metres, while cooked food was now being supplied to the men (Business Standard, 2023).
On the same day, the National Highways Authority of India ordered a safety audit of all under-construction tunnels (Business Standard, 2023). It was an early sign that the rescue was also becoming an inquiry into how tunnels are built.
Then the machine ran into trouble. Iron girders buried in the rubble blocked the auger on 23 November. A day later, its shaft and blade were damaged. On 25 November, the stuck machine was partly removed, and the workers were put in contact with their families. By 26 November, with the removal of the auger slowing everything, officials were focusing on other routes (Business Standard, 2023). Meanwhile, preparations for the moment of rescue continued: an eight-bed health centre inside the tunnel, a mud road re-laid for ambulances, and a ward with 41 oxygen-supported beds at the community health centre in Chinyalisaur, about 30 kilometres away (Business Standard, 2023).
On 27 November, with the machines beaten, the final stretch was handed to a group of men whose craft is officially illegal. Rat-hole miners, who dig narrow tunnels by hand, arrived to work alongside army engineers. They had been called in only after more than two weeks of failed attempts with heavy machinery (CBS News, 2023).
Business Standard reported that 12 men skilled in the technique were flown in from Delhi, and that they worked inside an 800-millimetre pipe with shovels and special tools, with a blower supplying air (Business Standard, 2023). Al Jazeera described six miners working in two teams of three. In each team, one person drilled, a second gathered the debris, and a third pushed it out of the pipe, and the effort took more than 24 hours (Al Jazeera, 2023). The two reports differ on the numbers, and they also differ on how much rubble the miners removed. One account says the last two metres, another says the final 10 to 12 metres, and a third says 17 metres (Business Standard, 2023; Business Standard, 2023b; The Tribune, n.d.). A careful writer should present these as reported figures, not as settled fact.
Rat-hole mining is a technique in which people dig small, narrow shafts by hand, mostly for coal. India’s National Green Tribunal banned it in 2014 as unscientific, though it continues in several states, especially in the northeast (Business Standard, 2023). It has a deadly record. Al Jazeera reported that at least 15 miners died in a flooded Meghalaya mine in 2019 after being trapped for more than a month, and that rights groups say 10,000 to 15,000 people died in such mines between 2007 and 2014 (Al Jazeera, 2023).
That contrast is the uncomfortable heart of the story. A method judged too dangerous for the economy turned out to be the one that finished the rescue. Some of the men said they had learned the skill in Delhi and were not coal miners at all (Al Jazeera, 2023). One of them, Nasir Hussain, said that when the breakthrough came, the miners hugged the trapped workers as if they were family. A rescue team leader, Wakil Hassan, said that the workers’ condition was fine (Al Jazeera, 2023). The lesson is not that the banned technique is safe. It is that skilled hands, and the people who have them, deserve to be recognised, trained and protected, not treated as an embarrassment until they are needed.
At about 7 pm on 28 November, rescuers broke through the last of the rubble. The workers were brought out one by one on wheeled stretchers through a steel pipe, and ambulances waited at the tunnel mouth (Business Standard, 2023).
The attention faded quickly, but the lives of the 41 men kept changing. In August 2024, ThePrint reported that only nine of the rescued workers had returned to the site, all of them employees of Navayuga. Most had been reluctant to go back when construction resumed in March 2024 (ThePrint, 2024a).
The Uttarakhand government announced Rs 1 lakh in compensation for each trapped worker. Navayuga’s representatives met the men at AIIMS Rishikesh and handed over cheques of Rs 2 lakh each, along with two months of paid leave (ThePrint, 2024a). The families spent the money in very personal ways: paying old debts, buying land, building houses, making fixed deposits for their children, getting married, and starting small businesses (ThePrint, 2024a).
Sanjay Basumatary, from Ramfalbil village in Assam’s Kokrajhar district, told ThePrint that he wanted to go back to Silkyara, but his family stopped him from returning to what they called the jaws of death. He bought six bighas of land for paddy and said working in his own fields gave him peace. He had also been promised a job by the Assam government. Instead, he received a tea cart, which, he said, now gathers dust in his courtyard and has only added to his family’s burden (ThePrint, 2024a).
Sushil, a Navayuga employee from Rohtas in Bihar, used his compensation to open a small shop selling items for prayers. He told ThePrint that he now earns half of what he did at the tunnel, but he lives near his wife and children. Bhagwan, from Odisha, who earned Rs 15,000 a month as a labourer in Uttarkashi, opened a grocery shop in his home state. Bishal, from Mandi in Himachal Pradesh, bought a life insurance policy and renovated his house, and said he might return to the site in future (ThePrint, 2024a).
Not every promise was kept. State governments had pledged houses, land and jobs when the world was watching. Manjeet, from Lakhimpur Kheri in Uttar Pradesh, received one acre of land, but he told ThePrint that the work and house promised to him never came. Officials, he said, used to visit and inspect, and then disappeared. Sushil put it more bitterly, saying that politicians came, gave scarves, took photographs and left (ThePrint, 2024a). A nodal officer quoted in the same report said that inspecting officials had found none of the workers eligible for a house under the criteria, and a Jharkhand labour department official said that the department’s job had been to bring the men back safely.
A smaller group went back to the tunnel. They told ThePrint that they could find no other work and had to feed their families. One of them said his family believes he works on a bridge, and another said his wife now has the phone number of the company’s human resources team so that she worries less (ThePrint, 2024a). In April 2025, Uttarakhand’s chief minister said that 15 or 16 of the 41 men were still working at the tunnel (The Tribune, 2025). The difference between that figure and the nine reported in 2024 is a reminder that such numbers change, and they should always be dated.
In the days after the rescue, the cause was unclear. The government promised an inquiry, while theories circulated about a landslide, a blast, and the hasty development of a fragile mountain region (Business Standard, 2023). A member of an expert panel told Reuters that the tunnel had no emergency exits and had been built through a geological fault (Al Jazeera, 2023).
By February 2024, the government had issued show-cause notices to the design consultant, the authority’s engineer, the construction contractor and supervising officials of NHIDCL, after an expert committee submitted a preliminary report. The road transport minister told Parliament in February 2024 that the National Highways Authority of India had also carried out a preliminary safety audit of all existing and ongoing tunnel projects (The Week, 2024).
The final report was submitted to the road ministry on 20 September 2024 by a five-member committee headed by R. K. Dhiman, an additional director general of the Border Roads Organisation. According to ThePrint, which reviewed its findings, the committee held NHIDCL, the contractor and the independent authority engineer responsible for lapses that led to what it called a national crisis. It said that a collapse that had been developing for four years went unnoticed by everyone, and that the negligence was “profound” (ThePrint, 2024b).
The committee’s findings, as reported, were specific. The technical parameters for the bid were finalised without geotechnical investigation. Shear zones, areas where rock walls slip past each other, were flagged in an interpretive report, but no advance probing was proposed or seen at the site. Incorrect rock-mass ratings were used to keep the rock in Class IV instead of the poorer Class V, which the committee said could probably be a reason for the many collapses. It recorded 21 collapses in the four years since work began, which it called unusual for a tunnel project (ThePrint, 2024b).
The most serious finding concerned escape. The contract had specified a two-way tunnel with a separate escape passage. In July 2020, NHIDCL changed the design to a one-way tunnel with a central partition wall, and the ventilation system was changed to a cheaper type, eliminating the egress tunnel. The committee said that the absence of a dedicated escape passage violated safety provisions for long tunnels. It noted that the ventilation originally specified costs between Rs 5 crore and Rs 6 crore per kilometre, against Rs 2 crore to Rs 2.5 crore for the system that replaced it (ThePrint, 2024b).
The report also pointed to warnings that were not heeded. The committee also said that the contractor had deliberately misrepresented monitoring data and failed to maintain basic safety infrastructure. A 2021 note by NHIDCL’s then managing director recorded that the tunnel had already suffered nine collapses, and that it was lucky there had been no c. The same note expected the contractor to drive through the tunnel by late 2022 (ThePrint, 2024b). The committee recommended that responsible officials be identified for penal action, and that the time lost to the collapse not be treated as force majeure, which means that the financial consequences should fall on the contractor (ThePrint, 2024b).
A fair account must note a limit. These findings come from a committee report as reviewed and reported by ThePrint. When that article was published, the journalist reported that comments had been sought from NHIDCL, Navayuga and the authority engineer, and the version I read did not carry their responses. Readers who want to go further should look for the companies’ and the agency’s replies, and for any later legal or administrative outcome.
An earlier preliminary account, reported by the Times of India, had made similar points. It said that the contractor had not obtained approval for its work method from the authority’s engineer, that too few sensors and instruments had been installed during re-profiling, and that cavities had appeared on two earlier occasions. It recommended a national tunnel centre, a new standard operating procedure for tunnel safety, and a shared geological framework (India Blooms, n.d.).
Not everyone in Silkyara looks to engineering reports for an explanation. ThePrint reported that many locals believe the collapse came from the anger of Baba Boukhnag, a local deity whose temple was demolished for the construction. When the first rescue attempts failed, the company asked a priest to perform a special puja, and a new temple was being built at the tunnel’s mouth (ThePrint, 2024a). In April 2025, when the tunnel’s excavation was completed, the chief minister said that it would be renamed after the deity (The Tribune, 2025).
This is not a footnote. It shows how a disaster is understood by the people who live beside it. Reports and rituals can sit side by side, and a project that ignores either one risks losing the trust of the community that hosts it.
The project has not been smooth. ThePrint reported that work began on 9 July 2018, with an original completion date of 8 July 2022, and that after the collapse a new deadline of 28 January 2026 was fixed. By August 2024, it said, only about 60 per cent of the work was done (ThePrint, 2024b). The contract itself had been awarded at Rs 853.79 crore, nearly 24 per cent below the tender cost of Rs 1,119.69 crore (ThePrint, 2024b).
On 16 April 2025, excavation from both ends met, and the Union Minister called the breakthrough historic (Daily Excelsior, 2025). I could not confirm from the sources I found whether the tunnel has since opened to traffic, and anyone repeating its current status should check the latest official statement.
The following lessons are my own reading of the evidence, not the findings of any official body.
The image of 28 November 2023 is a worker emerging into floodlights, greeted with garlands and applause. The image from 2024 is quieter: a tea cart in a courtyard in Assam, gathering dust. Both are true. One shows what a country can do when it focuses its attention. The other shows what happens when attention moves on.
Three years on, the 41 men are no longer a headline, but their story is still unfinished. The tunnel is closer to completion, the investigations have been written, and the workers have built new lives, some in the fields and shops of their home villages, and some back at the tunnel. The real measure of the rescue will be whether the next tunnel in the Himalaya has an escape route, whether the next warning is heard, and whether the next group of workers is remembered after the last camera has gone.